(A).Thermal Power Stations (2280 MW)

1

Korba East Thermal Power Station (440 MW)

Power House No. II

I

50

5-Sep-1966

 

II

50

16-May-1967

 

III

50

23-Mar-1968

 

IV

50

31-Oct-1968

 

Total

200

 

 

Power House No. III

I

120

27-Apr-1976

 

II

120

5-Apr-1981

 

Total

240

 

 

 

 

 

 

 

 

2

Korba East, Dr. Shyama Prasad Mukherjee Thermal Power Station (500 MW)

 

I

250

30-Mar-2007

27-Jun-2008

 

II

250

11-Dec-2007

30-Nov-2008

 

Total

500

 

 

 

 

 

 

 

 

3

Korba West, HasdeoThermal Power Station (840 MW)

 

I

210

21-Jun-1983

 

 

II

210

31-Mar-1984

 

 

III

210

26-Mar-1985

 

 

IV

210

13-Mar-1986

 

 

Total

840

 

 

   4

Korba West Extension 500 MW TPS

V

  500

 

 

                        

                        05-Sep-2013

(B).Hydel Power Stations (138.70 MW)

1

Mini-Mata Hasdeo Bango Hydel Power Station (120 MW)

 

I

40

21-Mar-1994

 

 

II

40

21-Nov-1994

 

 

III

40

11-Jan-1995

 

 

Total

120

 

 

 

 

 

 

 

 

2

Gangrel Hydel Power Station (10 MW)

 

I

2.5

2-Apr-2004

28-Jul-2004

 

II

2.5

29-Jun-2004

4-Aug-2004

 

III

2.5

17-Oct-2004

3-May-2005

 

IV

2.5

5-Nov-2004

23-May-2005

 

Total

10

 

 

 

 

 

 

 

 

3

Sikasar Hydel Power Station (7 MW)

 

I

3.5

3-Sep-2006

 

 

II

3.5

3-Sep-2006

 

 

Total

7

 

 

 

 

 

 

 

 

4

Korba West Mini/ Micro Hydel Power Station (1.7 MW)

 

I

0.85

12-Jan-2003

 

 

II

0.85

29-May-2009

4-Aug-2009

 

Total

1.7

 

 

(C).Other Power Stations (6 MW)

1

Bhoramdev Co-Gen, Kawardha (6 MW)

 

I

6

10-Aug-2006

 

 

Total

6

 

 

 

                      Grand Total (A+B+C)

2424.7