Sr. No. | Tender Issuing Office | Tender Notice No. | Scope of Work | Estimated Cost(Rs.) | Earnest Money Deposit (Rs.) | Closing Date & Time for Submission of Tender | Date & Time of Opening of Tender | S.no | LINK | open time | Subm time | View Tender Document | Remark/RFx ID for e-Bidding |
1
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/88 | Annual work of monitoring and patrolling of ash dyke Dindolbhata 1x500 MW Extn. HTPS, CSPGCL, Korba West. | 807120 | 8100 | 09/04/2025 03:00PM | 11/04/2025 04:00PM | 26368 |
| 04:00PM | 03:00PM |
| 8100041707 |
2
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/89 | Annual work of watch & ward of civil site office of ash dyke Dindolbhata 1x500 MW Extn. HTPS, CSPGCL, Korba West. | 567400 | 5700 | 09/04/2025 03:00PM | 11/04/2025 04:00PM | 26371 |
| 04:00PM | 03:00PM |
| 8100041731 |
3
| E.D.(S&P:Gen) Raipur | TN-366/EP-425 | Collecting tank with internal hard facing for ash handling plant at 1x500MW HTPS Korba West | | 23000 | 15/04/2025 03:00PM | 15/04/2025 03:30PM | 26055 |
| 03:30PM | 03:00PM |
| 8100041145 |
4
| E.D.(Civil-Project-I) Raipur | no 04-02/489 Raipur Dated 27.03.2025 | Deployment of Manpower (Computer Operator, ministerial staff & Peon) on contract basis for a period of one year for O/o ED (Civil-Project-I) CSPGCL Raipur. | 2358631/- | 23600/- | 23/04/2025 03:00PM | 25/04/2025 03:00PM | 26611 |
| 03:00PM | 03:00PM |
| 8100042277 |
5
| C.E.(Civil) Raipur | 04-04/W/2648 | Supply and fixing of radial gate no. 01 arm and make it in auto operative condition at 2x850 KW MHP, HTPS, CSPGCL, Korba West | 650000 | 6500 | 07/04/2025 03:00PM | 09/04/2025 04:00PM | 26375 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/ 2024/184 Rfx 8100041512 |
6
| C.E.(Civil) Raipur | 04-04/W/2873 | Annual repair and maintenance of carpentary work related to power house and other auxiliary building at 4x210MW, HTPS, CSPGCL, Korba West. | 455000 | 4600 | 17/04/2025 03:00PM | 21/04/2025 04:00PM | 26603 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/2024/200 Rfx 8100042227 |
7
| C.E.(Civil) Raipur | 04-04/W/2873 | Urgent repair and maintenance work of clear water reservoir and clarriflocculator of DM plant area at 4x210MW, HTPS, CSPGCL, Korba West. | 275000 | 2800 | 17/04/2025 03:00PM | 21/04/2025 04:00PM | 26602 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/2024/199 Rfx 8100042303 |
8
| C.E.(Civil) Raipur | 04-04/W/2873 | Pre- monsoon & during monsoon cleaning of drains, roof, rain water pipes & miscellaneous works in BTG & BOP building of 2x500 MW, ABVTPS, CSPGCL, Janjgir Champa | 499000 | 5000 | 17/04/2025 03:00PM | 21/04/2025 04:00PM | 26601 |
| 04:00PM | 03:00PM |
| CEC/ABVTPS-MRW/W/2024/198 Rfx 8100042310 |
9
| C.E.(Civil) Raipur | 04-04/W/2873 | Replacement of damaged & rusted fencing of the Sub Station located at KTPS plant at DSPM-TPS, CSPGCL, Korba East | 488000 | 4900 | 17/04/2025 03:00PM | 21/04/2025 04:00PM | 26600 |
| 04:00PM | 03:00PM |
| CEC/DSPM-KE/W/2024/197 Rfx 8100042306 |
10
| E.D.(S&P:Gen) Raipur | E-TENDER NOTICE NO. TN-475/24-25 | Work contract for Painting with epoxy based polyurethane paint of support structure of cable tray from Service building area to compressor pp house area up to ESP#1 area, DSPM TPS, KE. | 2002811.00 | 20100.00 | 24/04/2025 03:00PM | 24/04/2025 03:30PM | 26597 |
| 03:30PM | 03:00PM |
| 8100042344(Without RLA) |
11
| E.D.(S&P:Gen) Raipur | TN-437/MW-505/24-25 | Work of Conducting post Environment Impact Assessment (EIA) work/study at ABVTPS, CSPGCL, Marwa. | 2596000 | 26000 | 11/04/2025 03:00PM | 11/04/2025 03:30PM | 26339 |
| 03:30PM | 03:00PM |
| 8100041734 (With RLA) |
12
| E.D.(S&P:Gen) Raipur | TN-437/MW-504/24-25 | Supply & erection of 50 KL capacity MS tank along with accessories for storage of potable water at 2x500MW, ABVTPS, Marwa. | 2221834 | 22300 | 11/04/2025 03:00PM | 11/04/2025 03:30PM | 26335 |
| 03:30PM | 03:00PM |
| 8100041732 (Without RLA) |
13
| E.D.(Finance) Raipur | E.D.(Fin)CSPGCL/2024/T-12 | Hiring of vehicle of category-II for O/o Executive Director (Fin.), CSPGCL Raipur. | | 5000 | 17/04/2025 03:00PM | 17/04/2025 03:30PM | 26581 |
| 03:30PM | 03:00PM |
| 8100042359 |
14
| C.E.(Civil) Raipur | 04-04/W/2610 | Providing and fixing new drum barrier in place of damaged drum barrier No. 01, 02 & 03 at HTSP, CSPGCL, Korba West. | 6705000 | 5000 | 04/04/2025 03:00PM | 07/04/2025 04:00PM | 26308 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/2024/170 Rfx 8100041316 |
15
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/80 | Providing cement concrete surface at turnings & junctions over bund top at RL 313.00 M of lagoon 1A & 1B and WNN surface over bund top at RL 313.00 M of lagoon 2 at ash dyke Jhabu HTPS, CSPGCL, Korba West. | 6343000 | 63500 | 07/04/2025 03:00PM | 09/04/2025 04:00PM | 26298 |
| 04:00PM | 03:00PM |
| 8100041548 |
16
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/76 | Utilization of fly ash by filling in various low laying area within a distance of 50 Km from ash silo of 1x500 MW Extn. HTPS, CSPGCL, Korba West. | 44005000 | 440100 | 07/04/2025 03:00PM | 09/04/2025 04:00PM | 26247 |
| 04:00PM | 03:00PM |
| 8100041609 |
17
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/79 | Utilization of fly ash by filling in various low laying area within a distance of 50 Km from ash silo situated at 4x210 MW HTPS, CSPGCL, Korba West. | 44534000 | 445400 | 07/04/2025 03:00PM | 09/04/2025 04:00PM | 26246 |
| 04:00PM | 03:00PM |
| 8100041482 |
18
| E.D.(S&P:Gen) Raipur | TN-366/EP-424 | Strut pipes for flue gas/air ducts at 1x500MW HTPS, Korba West | | 37000 | 02/04/2025 03:00PM | 02/04/2025 03:30PM | 26054 |
| 03:30PM | 03:00PM |
| 8100041142 |
19
| E.D.(S&P:Gen) Raipur | TN-433/2024-25, CP-554/24-25 | Procurement of LTSH Upper Bank Coils & Economiser Upper Bank Coils for 1x500 MW, HTPS, KW Extn. | | 500000/- | 15/04/2025 03:00PM | 15/04/2025 03:30PM | 26556 |
| 03:30PM | 03:00PM |
| 8100042120 (With RLA) |
20
| C.E.(Civil) Raipur | 04-04/W/2779 | Providing and fixing chain link fencing in front of chemical wing near bulk acid tank area at 4x210MW HTPS, CSPGCL, Korba West | 569000 | 5700 | 11/04/2025 03:00PM | 15/04/2025 04:00PM | 26555 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/2024/195 Rfx 8100041727 |
21
| C.E.(Civil) Raipur | 04-04/W/2779 | Annual supply of various material, mason gang, carpentry gang, plumber gang, valve operator for pump operation and for various routine maintenance work at BTG and power house boundary wall area at 2x500MW, ABVTPS, CSPGCL, Janjgir Champa | 2096000 | 21000 | 11/04/2025 03:00PM | 15/04/2025 04:00PM | 26554 |
| 04:00PM | 03:00PM |
| CEC/ABVTPS-MRW/W/2024/194 Rfx 8100041900 |
22
| C.E.(Civil) Raipur | 04-04/W/2780 | Extension of existing hospital building at AB type colony DSPM-TPS, CSPGCL, Korba East | 4670000 | 46700 | 11/04/2025 03:00PM | 15/04/2025 04:00PM | 26553 |
| 04:00PM | 03:00PM |
| CEC/DSPM-KE/W/ 2024/196 Rfx 8100041916 |
23
| E.D.(S&P:Gen) Raipur | TN-445/24-25 EW- 531/24-25 | Deployment of 43 Nos. ITI/Skilled manpower for Assisting Operation of CHP:INT, 1x500 MW, HTPS, Korba West. | | 121000 | 02/04/2025 03:00PM | 02/04/2025 03:30PM | 26551 |
| 03:30PM | 03:00PM |
| 8100041891 |
24
| C.E.(Civil: AU&PC) | EDC/AU&PC/DSPM-KE/W/2024/82 | Augmenting the existing capacity by making the peripheral with ash in the inner side of the lagoon-02 at Gorhi/Pandripani ash dyke of DSPM-TPS, Korba East. | 808166 | 8100 | 01/04/2025 03:00PM | 03/04/2025 04:00PM | 26234 |
| 04:00PM | 03:00PM |
| 8100041550 |
25
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/83 | Hiring of Bulldozer for spreading and levelling of ash dumped by CSPGCL at Manikpur Open Cast Mines for ash utilization works CSPGCL, Korba East & West. | 8269000 | 82700 | 28/03/2025 03:00PM | 01/04/2025 04:00PM | 26299 |
| 04:00PM | 03:00PM |
| 8100041537 |
26
| C.E.(Civil: AU&PC) | EDC/AU&PC/DSPM-KE/W/2024/81 | Filling the earth at top bund level to fill the ruts and protect the surcharge ash accumulated above the bund level at Gorhi/Pandripani ash dyke at DSPM-TPS, CSPGCL, Korba East. | 1909993 | 19100 | 01/04/2025 03:00PM | 03/04/2025 04:00PM | 26229 |
| 04:00PM | 03:00PM |
| 8100041538 |
27
| E.D.(S&P:Gen) Raipur | E-TENDER NOTICE NO. TN-474/24-25 | Deployment of Trained Fire Personal for round the clock duty in three shifts for Firefighting duty, fire prevention, Checking and updating of fire Equipment in DSPM TPS & KTPS, CSPGCL Korba East. | 13510818.00 | 67600/- | 11/04/2025 03:00PM | 11/04/2025 03:30PM | 26543 |
| 03:30PM | 03:00PM |
| 8100042228(Without RLA) |
28
| E.D.(S&P:Gen) Raipur | E-TENDER NOTICE NO. TN-474/24-25 | AOH of Boiler Pressure Part of unit #1, for 250MW BHEL Boilers of DSPM TPS, Korba East | 15547033.00 | 155500.00 | 11/04/2025 03:00PM | 11/04/2025 03:30PM | 26544 |
| 03:30PM | 03:00PM |
| 8100042229 (With RLA) |
29
| E.D.(Civil-Project-I) Raipur | 04-02/GP-III/W/212-A/280 dated 21.02.2025 | Annual work of providing services of Khansama, helping assistance to him and housekeeping of rest house along with sweeping and cleaning complete etc. for day to day operation of Rest House at CMDC, CSPGCL, Gharghoda, Distt.-Raigarh (C.G.) | 996548 | 10000 | 26/03/2025 03:00PM | 28/03/2025 03:00PM | 26224 |
| 03:00PM | 03:00PM |
| 8100041659 |
30
| E.D.(S&P:Gen) Raipur | TN- 433 DW-559/24-25 | Deployment of skilled labours (ITI in Mechanical) round the clock (27 persons) for Boiler, Turbine, FOPH and other Mechanical operation at DSPM TPS Korba East | 15199742.00 | 76000.00 | 16/04/2025 03:00PM | 16/04/2025 03:30PM | 26536 |
| 03:30PM | 03:00PM |
| DW-559/24-25, 8100042134 Without RLA |
31
| E.D.(S&P:Gen) Raipur | 03-03/ TN-433/EW-555/24-25 | Day to Day Electrical Lighting Maintenance of 4x210 MW, PH-I & PH-II, 1x500 MW Extn., New Admin Building, HTPS, Colony Parisar for HTPS, KW | | | 15/04/2025 03:00PM | 15/04/2025 03:30PM | 26534 |
| 03:30PM | 03:00PM |
| 8100042077 |
32
| Addl.CE (Gen) - Gare Palma-III | 19-13/GP3/GEN/P/T-01/24-25/26 | Purchase of 01 No. 2 Ton split type Air conditioner for office of Addl. CE. (Gen), GP-III, Coal Block, Gharghoda. | 80640 | 810 | 16/04/2025 03:30PM | 16/04/2025 04:00PM | 26519 |
| 04:00PM | 03:30PM |
| |
33
| Addl.CE (Gen) - Gare Palma-III | 19-13/GP3/GEN/W/T-01/24-25/19 | Hiring of one No. car category-II vehicle for Addl. CE (Gen) Gare Pelma Sector-III , gharghoda for the period of 2 year with Driver, consumable, Disel/Petrol etc. | 1039600.00 | 10396 | 04/04/2025 03:30PM | 04/04/2025 04:00PM | 26215 |
| 04:00PM | 03:30PM |
| |
34
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/64 | Utilization of fly ash by filling in various low laying area within a distance of 50 Km from ash silo of 1x500 MW Extn. HTPS, CSPGCL, Korba West. | 40351000 | 403600 | 02/04/2025 03:00PM | 04/04/2025 04:00PM | 25878 |
| 04:00PM | 03:00PM |
| 8100040878 |
35
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/62 | Fly ash utilization by disposal of fly ash in low laying areas at nearby location within 50 Km lead from ash silo situated at 4x210 MW, HTPS, CSPGCL, Korba West. | 37335000 | 373400 | 02/04/2025 03:00PM | 04/04/2025 04:00PM | 25837 |
| 04:00PM | 03:00PM |
| 8100040812 |
36
| E.D.(S&P:Gen) Raipur | TN-433/DW-560/24-25 | O&M Work for Ash Handling System of 2x250 MW, DSPM TPS, Korba East | 39002155 | 195100 | 11/04/2025 03:00PM | 11/04/2025 03:30PM | 26508 |
| 03:30PM | 03:00PM |
| 8100042142 (With RLA) |
37
| E.D.(S&P:Gen) Raipur | TN-433 CP-499 | Procurement of Grinding Rolls & Bull Ring Segments for XRP-883 Coal Mills of DSPM TPS, Korba East and XRP-803 Coal Mills of HTPS, KW and BRS for XRP-1003 Coal Mills of 1x500 MW, Extn. KW and ABVTPS, Marwa | 49300000/- | 495000/- | 09/04/2025 03:00PM | 09/04/2025 03:30PM | 26506 |
| 03:30PM | 03:00PM |
| 8100042112 |
38
| C.E.(Civil: AU&PC) | EDC/AU&PC/ABVTPS-MRW/W/2024/92 | Utilization of fly ash by transportation to brick/tile manufacturing industries upto 50 Km from ash silo and dump area of 2x500 MW ABVTPS, CSPGCL, Marwa-Tendubhata. | 31995000 | 320000 | 07/04/2025 03:00PM | 09/04/2025 04:30PM | 26497 |
| 04:30PM | 03:00PM |
| 8100042007 |
39
| E.D.(S&P:Gen) Raipur | 03-03/ TN-450/DP-538/24-25 (RFx-8100042000) | Procurement of Dew Point Apparatus, Portable DO Analyzer & PH Meter for DSPM TPS,Korba East. | 16.4 Lac | 16400 | 04/04/2025 03:00PM | 04/04/2025 03:30PM | 26478 |
| 03:30PM | 03:00PM |
| (RFx-8100042000) |
40
| E.D.(Project) Raipur | 03-05/PROJECT/T-04/2024-25/780 | SUPLLY OF 02 NOS STEEL ALMIRAH & 02 NOS EXECUTIVE REVOLVING CHAIR FOR THE O/O ED(PROJECT) CSPGCL,RAIPUR | | 1000 | 28/03/2025 03:00PM | 28/03/2025 04:00PM | 26028 |
| 04:00PM | 03:00PM |
| |
41
| E.D.(Project) Raipur | 03-05/PROJECT/T-03/2024-25/779 | SUPPLY OF 08 NOS VISITOR CHAIR FOR THE O/O ED(PROJECT) CSPGCL, RAIPUR | | 1000 | 28/03/2025 03:00PM | 28/03/2025 04:00PM | 26027 |
| 04:00PM | 03:00PM |
| |
42
| E.D.(S&P:Gen) Raipur | TN-458/MW-547/24-25 | Work Contract of (i) assistance in railway track point operation along with checking (Oiling & greasing etc) of all track point inside & outside of plant from Naila end to plant area round the clock (ii) assistance in gate operation and (iii) Boom barrier operation at ABVTPS round the clock for coal Transportation of 2x500 MW ABVTPS, CSPGCL, Marwa | 3513099 | 17600 | 04/04/2025 03:00PM | 04/04/2025 03:30PM | 26466 |
| 03:30PM | 03:00PM |
| 8100042068 (With RLA) |
43
| E.D.(O&M:Gen) Raipur | 03-01/O&M/MIS-IT/TS-12 dtd 12.03.2025 | Work proposal for Annual Maintenance Contract(AMC) for CSPGCL Power App Server, Firewall & internet connection at O/o ED (O&M), CSPGCL, Raipur | | 4200 | 01/04/2025 04:00PM | 01/04/2025 04:30PM | 26464 |
| 04:30PM | 04:00PM |
| |
44
| E.D.(S&P:Gen) Raipur | E-TENDER NOTICE NO. TN-458/24-25 | Work Contract for environmental pollution monitoring works of air, water, noise & waste/used oil & deployment of adequate man-power for environmental related works at DSPM TPS, Korba East. | 3934680/- | 19700/- | 04/04/2025 03:00PM | 04/04/2025 03:30PM | 26463 |
| 03:30PM | 03:00PM |
| 8100042069 (With RLA) |
45
| E.D.(Finance) Raipur | 05-05/R&P Fin/01/2025 | Invitation of offers from RBI Regulated Entities/ Banks/Financial Institutions for Refinancing of Term Loan | 3030 Crore | 0 | 25/04/2025 05:00PM | 28/04/2025 03:00PM | 26460 |
| 03:00PM | 05:00PM |
| |
46
| C.E.(Civil) Raipur | 04-04/W/2739 | Supply & procurement of Computer, Printer, Cartridge & UPS for O/o E.E. (Civil) Dn.-II, at HTPS, CSPGCL, Korba West. | 281000 | 2900 | 02/04/2025 04:00PM | 04/04/2025 04:15PM | 26458 |
| 04:15PM | 04:00PM |
| CEC/HTPS-KW/W/2024/193 |
47
| C.E.(Civil: AU&PC) | EDC/AU&PC/W/2024/91 | Providing service of one no. Helper & one no. Data Entry Operator from out sourcing for the O/o E.D. (Civil) AU&PC, Dangania, CSPGCL, Raipur (Shed No. 02). | 482856 | 5000 | 01/04/2025 03:00PM | 03/04/2025 04:00PM | 26448 |
| 04:00PM | 03:00PM |
| NIT No. 03-15/W/1910 Raipur dt. 10.03.2025. |
48
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/90 | Construction of RCC pit to develop Ash Water Recovery System (AWRS) at Jhabu ash dyke HTPS, CSPGCL, Korba West. | 20768000 | 207700 | 02/04/2025 03:00PM | 04/04/2025 04:00PM | 26447 |
| 04:00PM | 03:00PM |
| 8100041969 |
49
| E.D.(S&P:Gen) Raipur | TN- 438/24-25 DW-527/24-25 | Work contract for Assistance in Mechanical maintenance of CHP at DSPM TPS Korba East | 6566452.00 | 32800 | 03/04/2025 03:00PM | 03/04/2025 03:30PM | 26440 |
| 03:30PM | 03:00PM |
| DW-527/24-25 8100041811(With RLA) |
50
| E.D.(S&P:Gen) Raipur | TN- 438/24-25 , HW-535/24-25 | “Daily Cleaning of Mill Area & Platform, Removal & Transportation of Reject from Unit no. 1 to 4 at HTPS, Korba (West)” | 9800891.20 | 49100 | 04/04/2025 03:00PM | 04/04/2025 03:30PM | 26439 |
| 03:30PM | 03:00PM |
| HW- 535/24-258100041918(With RLA) |
51
| E.D.(S&P:Gen) Raipur | TN- 438/24-25 , HW-528/24-25 | AOH work of Tubular Air Heaters of 2x210 MW ABL make Boilers of Unit No. 3&4 of HTPS, Korba West | 5811680 | 58200 | 03/04/2025 03:00PM | 03/04/2025 03:30PM | 26438 |
| 03:30PM | 03:00PM |
| HW-528/24-25 8100041814(With RLA) |
52
| E.D.(S&P:Gen) Raipur | TN- 438/24-25 , HW-513/24-25 | AOH work of 8.5 E 9 Mills & Coal dust circuit of 2x210 MW ABL Make Boilers of Unit No. 3&4, HTPS, Korba West. | 6068123.80 | 60100 | 03/04/2025 03:00PM | 03/04/2025 03:30PM | 26437 |
| 03:30PM | 03:00PM |
| HW-513/24-25 8100041718(With RLA) |
53
| E.D.(S&P:Gen) Raipur | E-TENDER NOTICE NO. TN-438/24-25 | Work Contract for Chemical shifting dosing and miscellaneous work associated with Pre Treatment D.M. plant, drinking water plant, DSPM TPS, CSPGCL, Korba East. | 5070200.00 | 25300/- | 03/04/2025 03:00PM | 03/04/2025 03:30PM | 26436 |
| 03:30PM | 03:00PM |
| 8100041897 (With RLA) |
54
| E.D.(S&P:Gen) Raipur | CP-374/ TN-321/ 24-25 | Procurement of Pipe Conveyor Belt for 3rd Stream Line for HTPS, Korba West. | 22406535 | 224100/- | 17/03/2025 03:00PM | 17/03/2025 03:30PM | 25775 |
| 03:30PM | 03:00PM |
| Rfx no. - 8100040667 (with RLA) |
55
| C.E.(Civil: AU&PC) | EDC/AU&PC/ABVTPS-MRW/W/2024/71 | Ash utilization by ash filling in Abandoned quarry up to a lead of 50 Km from ash dyke of 2x500 MW ABVTPS Marwa. | 35207000 | 352100 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26040 |
| 04:00PM | 03:00PM |
| 8100041209 |
56
| E.D.(S&P:Gen) Raipur | TN-445/MW-533/24-25 | Day to day routine, preventive & emergency breakdown mechanical maintenance of Turbine & auxiliaries of Unit 1&2 of 2x500 MW, ABVTPS, CSPGCL, Marwa, Janjgir-Champa. | 17700826 | 89000 | 02/04/2025 03:00PM | 02/04/2025 03:30PM | 26415 |
| 03:30PM | 03:00PM |
| 8100041888(With RLA) |
57
| C.E.(HR) Raipur | 676/04.03.2025 | Supply & Installation of 06 nos. Split AC [04 nos. 1.5 Tonn & 02 nos. 2 Tonn] | | | 27/03/2025 04:00PM | 27/03/2025 04:30PM | 26413 |
| 04:30PM | 04:00PM |
| |
58
| C.E.(Civil) Raipur | 04-04/W/2690 | Day to day assistance in office works, movement & maintenance of files, receipt/dispatch etc. for O/o C.E. (Civil) CSPGCL, Dangania, raipur. | 430000 | 4300 | 26/03/2025 04:00PM | 27/03/2025 04:15PM | 26412 |
| 04:15PM | 04:00PM |
| CEC/Office/W/2024/192 |
59
| E.D.(S&P:Gen) Raipur | TN-346/24-25, MP-401 | Procurement of Unit Auxiliary Transformer (25 MVA, 21/6.6 KV, 3 Phase) with Fitting & accessories along with Transformer Oil (as per schedule) for CSPGCL. | | 500000 | 28/03/2025 03:00PM | 28/03/2025 03:30PM | 26407 |
| 03:30PM | 03:00PM |
| [8100041400](With RLA) |
60
| E.D.(C&RA) Raipur | 03-09/C&RA/T-02/122 dtd 04.03.2024 | Deployment of 02 number computer operator. | | 4300 | 24/03/2025 05:00PM | 26/03/2025 04:30PM | 26404 |
| 04:30PM | 05:00PM |
| |
61
| E.D.(S&P:Gen) Raipur | 03-03/ TN-437/EW-519/24-25 | Work Contract for Belt jointing by Hot Vulcanizing process and Belt Replacement/Addition & Belt Tuning for 1600 mm width pipe conveyor belt at CHP;EXT, HTPS, KWB. | | | 26/03/2025 03:00PM | 26/03/2025 03:30PM | 26402 |
| 03:30PM | 03:00PM |
| 8100041746 |
62
| E.D.(S&P:Gen) Raipur | 03-03/ TN-437/EW-518/24-25 | Work of In-Situ Servicing/Repairing/overhauling of Various High Pressure Valves (Min.1500 class or above), HPBP Spray Control BD & BPF valve and HPBP valve of HPBP system along with all consumable by using special purpose In-Situ cutting/Lapping Machine for Unit no. 5, 1x500 MW HTPS, KW. | | | 28/03/2025 03:00PM | 28/03/2025 03:30PM | 26401 |
| 03:30PM | 03:00PM |
| 8100041752 |
63
| E.D.(S&P:Gen) Raipur | 03-03/ TN-437/EW-517/24-25 | Supply, Installation and Commissioning of 02 nos. 30 Mtr High Mast lighting system at Conveyor 5A/B of CHP:EXT HTPS, CSPGCL, KWB. | | | 27/03/2025 03:00PM | 27/03/2025 03:30PM | 26398 |
| 03:30PM | 03:00PM |
| 8100041748 |
64
| E.D.(S&P:Gen) Raipur | 03-03/ TN-437/EW-516/24-25 | Hiring of one nos. Ambulance for round the clock duty in all three shifts for HTPS, Hospital CSPGCL KW. | | | 26/03/2025 03:00PM | 26/03/2025 03:30PM | 26397 |
| 03:30PM | 03:00PM |
| 8100041750 |
65
| E.D.(S&P:Gen) Raipur | 03-03/ TN-437/EW-515/24-25 | “Daily cleaning of TG Hall & its associated buildings of 1x500 MW, HTPS, KW” | | | 24/03/2025 03:00PM | 24/03/2025 03:30PM | 26396 |
| 03:30PM | 03:00PM |
| 8100041751 |
66
| E.D.(S&P:Gen) Raipur | 03-03/TN-442//EW-524/24-25 | Work of “Dosing of C.W. Chemicals and monitoring of cooling water parameters at 1x500 MW, HTPS, Korba West. | | | 28/03/2025 03:00PM | 28/03/2025 03:30PM | 26395 |
| 03:30PM | 03:00PM |
| 8100041757 |
67
| E.D.(S&P:Gen) Raipur | 03-03/TN-442//EW-523/24-25 | Day to day preventive general and breakdown maintenance of water system and DM plant of 1x500 MW, HTPS, KWB | | | 28/03/2025 03:00PM | 28/03/2025 03:30PM | 26394 |
| 03:30PM | 03:00PM |
| 8100041756 |
68
| E.D.(S&P:Gen) Raipur | 03-03/TN-442//EW-522/24-25 | Work of installation of conveyor structure canopy along with GI sheet, strips and fasteners with washer etc. for A & B stream of CHP-EXT, HTPS Korba West. | | | 28/03/2025 03:00PM | 28/03/2025 03:30PM | 26393 |
| 03:30PM | 03:00PM |
| 8100041754 |
69
| C.E.(Civil) Raipur | 04-04/W/2667 | Providing roofing canopy on conveyor head end gantry on conveyor no. 13 to 04 at Extn. CHP LDCC at HTPS, CSPGCL, Korba West | 8723000 | 87300 | 26/03/2025 03:00PM | 28/03/2025 04:00PM | 26391 |
| 04:00PM | 03:00PM |
| CEC/HTPS -KW/W/ 2024/173 Rfx 8100041753 |
70
| C.E.(Civil) Raipur | 04-04/W/2666 | Construction of RCC wall along conveyor 12 (Phase-II) at Extn. CHP at HTPS, CSPGCL, Korba West | 6428000 | 64300 | 26/03/2025 03:00PM | 28/03/2025 04:00PM | 26390 |
| 04:00PM | 03:00PM |
| CEC/HTPS -KW/W/ 2024/172 Rfx 8100041511 |
71
| C.E.(Civil) Raipur | 04-04/W/2678 | Supply and installation of split Air Conditioner units for office, meeting hall and retiring rooms at 4x2.5MW, HEP, Gangrel, CSPGCL, Dhamtari. | 420000 | 4200 | 24/03/2025 04:00PM | 26/03/2025 04:15PM | 26388 |
| 04:15PM | 04:00PM |
| CEC/Gangrel-HEP/W/2024/189 |
72
| C.E.(Civil) Raipur | 04-04/W/2678 | Supply and installation of split Air Conditioner units for office, meeting hall and retiring rooms at 2x3.5MW, HEP, Sikasar, CSPGCL, Gariyaband | 436000 | 4400 | 26/03/2025 04:00PM | 27/03/2025 04:15PM | 26387 |
| 04:15PM | 04:00PM |
| CEC/Siksar-HEP/W/2024/191 |
73
| C.E.(Civil) Raipur | 04-04/W/2675 | Providing and fixing of retro reflective radium sign board along with enameled pole and necessary foundation work for 4x2.5MW, HEP, Gangrel, Dhamtari. | 398000 | 4000 | 24/03/2025 04:00PM | 26/03/2025 04:15PM | 26386 |
| 04:15PM | 04:00PM |
| CEC/Gangrel-HEP/W/2024/188 |
74
| C.E.(Civil) Raipur | 04-04/W/2677 | Providing and fixing of retro reflective radium sign board along with enameled pole and necessary foundation work for 2x3.5MW, HEP, Sikasar, Gariyaband. | 398000 | 4000 | 26/03/2025 04:00PM | 27/03/2025 04:15PM | 26385 |
| 04:15PM | 04:00PM |
| CEC/Sikasar-HEP/W/2024/190 |
75
| C.E.(Civil) Raipur | 04-04/W/2654 | Construction of temporary bund in TRC for dewatering of TRC to facilitate inspection of Draft tube bend by OEM experts of BFL at 2x3.5MW HEP, Sikasar, Gariyaband. | 387000 | 3900 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26377 |
| 04:00PM | 03:00PM |
| CEC/Sikasar-HEP/W/2024/187 Rfx 8100041807 |
76
| C.E.(Civil) Raipur | 04-04/W/2654 | Replacement of broken, cracked & old AC sheet with profile sheet at filter house PH-III and Chemical house at KTPS, DSPM-TPS, CSPGCL, Korba East. | 418000 | 4200 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26376 |
| 04:00PM | 03:00PM |
| CEC/DSPM-KE/W/2024/186 Rfx 8100041789 |
77
| C.E.(Civil) Raipur | 04-04/W/2647 | Replacement of Gypsum board false ceiling from aluminium tile false ceiling in Ground, Second and Third floor of south wing 2x500 MW, ABVTPS, CSPGCL, Janjgir-Champa | 1319000 | 13200 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26374 |
| 04:00PM | 03:00PM |
| CEC/ABVTPS-MRW/ W/2024/ 183 Rfx 8100041669 |
78
| C.E.(Civil) Raipur | 04-04/W/2647 | Annual operation of SLRM center i/c daily collection of domestic waste from door to door of residential quarters and segregation of waste collected under solid waste management rules at HTPS, CSPGCL, Korba West | 1902000 | 19100 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26373 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/ 2024/ 182 Rfx 8100041678 |
79
| C.E.(Civil) Raipur | 04-04/W/2647 | Annual maintenance of lawn & garden inside power house premises 2x500 MW, ABVTPS, CSPGCL, Janjgir-Champa | 1698000 | 17000 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26372 |
| 04:00PM | 03:00PM |
| CEC/ABVTPS-MRW/ W/2024/ 181 Rfx 8100041689 |
80
| C.E.(Civil) Raipur | 04-04/W/2647 | Replacement of damaged/unservice- able roof sheets of shed no. 01 & 02 of 2x500MW, ABVTPS, CSPGCL, Janjgir-Champa | 1354000 | 13600 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26370 |
| 04:00PM | 03:00PM |
| CEC/ABVTPS-MRW/ W/2024/ 180 Rfx 8100041688 |
81
| C.E.(Civil) Raipur | 04-04/W/2647 | Raising height of balance length of boundary wall between Silo gate to watch tower no. 06 at 2x500MW, ABVTPS,CSPGCL, Janjgir-Champa | 1876000 | 18800 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26369 |
| 04:00PM | 03:00PM |
| CEC/ABVTPS-MRW/ W/2024/ 179 Rfx 8100041687 |
82
| C.E.(Civil) Raipur | 04-04/W/2647 | Provision of safety measures around dipole structures (Transformer structure) inside AB & CDEF type colony, DSPM-TPS, CSPGCL, Korba East | 1306000 | 13100 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26367 |
| 04:00PM | 03:00PM |
| CEC/DSPMKE/W/ 2024/178 Rfx 8100041679 |
83
| C.E.(Civil) Raipur | 04-04/W/2647 | Replacement of damaged door, window RCC Boxes Chhajja by profile sheet Chhajja in double story buildings in Zone ‘A’ at CD type colony, DSPM-TPS, CSPGCL, Korba East | 1493000 | 15000 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26366 |
| 04:00PM | 03:00PM |
| CEC/DSPMKE/W/ 2024/177 Rfx 8100041680 |
84
| C.E.(Civil) Raipur | 04-04/W/2647 | Chain link fencing from transformer yard to Raw water pump house, Raw water pump house, fire pump house & filter house PH-II & PH-III at retired KTPS to safe guard company’s property and prevent unauthorized entry, at DSPM-TPS, CSPGCL, Korba East | 2112000 | 21200 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26365 |
| 04:00PM | 03:00PM |
| CEC/DSPMKE/W/ 2024/176 Rfx 8100041324 |
85
| C.E.(Civil) Raipur | 04-04/W/2646 | Prevention of leakage/seepage from roofs at colony premises of 2x500 MW, ABVTPS, CSPGCL, Janjgir-Champa (Phase-I) | 2057000 | 20600 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26364 |
| 04:00PM | 03:00PM |
| CEC/ABVTPS-MRW/ W/2024/175 Rfx 8100041311 |
86
| C.E.(Civil) Raipur | 04-04/W/2645 | Annual work of carpenter gang for day to day maintenance of carpentry work of CD type, AB type, 100 units staff quarters & plumber gang for R&M of domestic line (Internal & External) in AB & CD type colony at DSPM-TPS, CSPGCL, Korba East | 1616000 | 16200 | 24/03/2025 03:00PM | 26/03/2025 04:00PM | 26362 |
| 04:00PM | 03:00PM |
| CEC/DSPM-KE/W/ 2024/174 Rfx 8100041497 |
87
| C.E.(Civil) Raipur | 04-04/W/2314 | Annual supply of horticultural inputs (Field material) for colony, VIP Rest House, Prakash Bhawan, 60 bedded Hospital, Central Garden, Erector Hostel, Nursery and other important places at HTPS, CSPGCL, Korba West | | | 17/03/2025 03:00PM | 19/03/2025 04:00PM | 26082 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/2024/171 Rfx 8100041338 |
88
| E.D.(S&P:Gen) Raipur | E-TENDER NOTICE NO. TN-437/24-25 | Deployment of Paramedical Staff at Occupational Health Center (OHC), DSPM TPS, CSPGCL,KE. | 2583833 | 25800.00 | 24/03/2025 03:00PM | 24/03/2025 03:30PM | 26350 |
| 03:30PM | 03:00PM |
| DW-506/24-258100041735 (Without RLA) |
89
| E.D.(S&P:Gen) Raipur | E-TENDER NOTICE NO. TN-437/24-25 | Work Contract for Assistance in operation of Effluent Treatment Plant & AWRS at DSPM TPS, KE &operation and maintenance of ETP at Main Hospital, CSPGCL, KE. | 4011386 | 20100.00 | 26/03/2025 03:00PM | 26/03/2025 03:30PM | 26349 |
| 03:30PM | 03:00PM |
| 8100041763 |
90
| C.E.(Civil) Raipur | 04-04/W/2649 | Annual maintenance of boundary wall of 1x500MW Extn., HTPS, CSPGCL, Korba West. | 320000 | 3200 | 21/03/2025 03:00PM | 24/03/2025 04:00PM | 26346 |
| 04:00PM | 03:00PM |
| CEC/HTPS-KW/W/2024/185 Rfx 8100041496 |
91
| E.D.(S&P:Gen) Raipur | TN- 437/24-25 HW-511 | AOH work of Ducts & Dampers of 2x210MW,ABL Boilers of U#3&4 of HTPS, KW. | 3013197.76 | 33200 | 24/03/2025 03:00PM | 24/03/2025 03:30PM | 26344 |
| 03:30PM | 03:00PM |
| HW-511/24-25 8100041742 (With RLA) |
92
| E.D.(S&P:Gen) Raipur | TN- 437/24-25 HW-510 | “Overhauling work of Motors & ESP of Unit no. 3&4 of PH-II, HTPS, KW. | 3314099 | 33200 | 24/03/2025 03:00PM | 24/03/2025 03:30PM | 26343 |
| 03:30PM | 03:00PM |
| HW-510/24-25 8100041741 (With RLA) |
93
| E.D.(S&P:Gen) Raipur | TN- 437/24-25 HW-509 | AOH Work of ID/FD/PA Fans of unit#3&4 of 4x210 MW, HTPS, KW. | 3113982.57 | 31200 | 24/03/2025 03:00PM | 24/03/2025 03:30PM | 26342 |
| 03:30PM | 03:00PM |
| HW-509/24-25 8100041739 (With RLA) |
94
| E.D.(S&P:Gen) Raipur | TN- 437/24-25 HW-508 | RYM work contract for EMD-2, (HT< Motors, ESP, Battery & Plant Lighting), PH-II, HTPS, KW. | 3979558.17 | 39800 | 24/03/2025 03:00PM | 24/03/2025 03:30PM | 26341 |
| 03:30PM | 03:00PM |
| HW-508/24-25 8100041738 (With RLA) |
95
| E.D.(S&P:Gen) Raipur | TN- 437/24-25 HW-507 | RYM work contract for EMD-I, PH-II. HTPS, CSPGCL,KW. | 4235610.80 | 42500 | 24/03/2025 03:00PM | 24/03/2025 03:30PM | 26340 |
| 03:30PM | 03:00PM |
| HW-507/24-258100041737 (With RLA) |
96
| E.D.(S&P:Gen) Raipur | TN-427/24-25, CP-526/24-25 | Procurement of High Pressure Economiser Coils (Upper and Lower) for 210 MW, BHEL Boilers, Unit #1, HTPS, KW. | | 500000/- | 28/03/2025 03:00PM | 28/03/2025 03:30PM | 26321 |
| 03:30PM | 03:00PM |
| 8100041771 (with RLA) |
97
| E.D.(S&P:Gen) Raipur | TN-427/24-25, CP-493/24-25 | Procurement of High Pressure LTSH Coils (Upper and Lower) for 210 MW, BHEL Boilers, Unit #2, HTPS, KW. | | 253000/- | 07/04/2025 03:00PM | 07/04/2025 03:30PM | 26320 |
| 03:30PM | 03:00PM |
| 8100041572 (with RLA) |
98
| E.D.(S&P:Gen) Raipur | TN-427/24-25, CP-492/24-25 | Procurement of Fully Killed ERW Air Heater Tubes for 210 MW ABL Boiler, U#4, HTPS, KW. | | 180000/- | 21/03/2025 03:00PM | 21/03/2025 03:30PM | 26319 |
| 03:30PM | 03:00PM |
| 8100041570 (With RLA) |
99
| E.D.(S&P:Gen) Raipur | No. 03-03/ TN-343/24-25/3742 ,Raipur, Dtd.03.01.2025 | Rewinding work of 0.4 KV, 3- Phase, LT Motors Stators of 4x210 MW, CSPGCL PH-I, HTPS, K.W. | 1604239.00 | 16100 | 17/03/2025 03:00PM | 17/03/2025 03:30PM | 25973 |
| 03:30PM | 03:00PM |
| HW-414/24-25, 8100041038(Without RLA) |
100
| E.D.(T&QA) Raipur | 03-10/T&QA/T-19/2025-26/111 dt. 25.02.2025 | Procurement of 02 nos all in one PC 02 NOS all in one printer along with UPS, for CE(T&QA) CSPGCL; Raipur | 221309 | 2500 | 17/03/2025 03:15PM | 17/03/2025 03:30PM | 26284 |
| 03:30PM | 03:15PM |
| |
101
| C.E.(Civil: AU&PC) | EDC/AU&PC/ABVTPS-MRW/W/2024/74 | Transportation of fly ash through bulker/capsules for Cement Industries from ash silos of 2x500MW, ABVTPS, CSPGCL, Marwa. | 141200000 | 500000 | 17/03/2025 03:00PM | 19/03/2025 04:00PM | 26225 |
| 04:00PM | 03:00PM |
| 8100041563 |
102
| C.E.(Civil: AU&PC) | EDC/AU&PC/DSPM-KE/W/2024/84 | Transportation of fly ash through bulker/capsules for Cement Industries from ash silo of 2x250 MW, DSPM-TPS, CSPGCL, Korba East. | 94440000 | 500000 | 17/03/2025 03:00PM | 19/03/2025 04:00PM | 26226 |
| 04:00PM | 03:00PM |
| 8100041558 |
103
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/87 | Transportation of fly ash through bulkers/capsules for Cement Industries from ash silo of 4x210 MW & 1x500 MW Extn., HTPS, Korba West, CSPGCL. | 94440000 | 500000 | 17/03/2025 03:00PM | 19/03/2025 04:00PM | 26228 |
| 04:00PM | 03:00PM |
| 8100041622 |
104
| E.D.(Civil-Project-I) Raipur | ED(CP-I)/2x660MW/W/2024-25/T-99 | Dismantling of store 1 & 2 of 1x500MW Extn. Unit, HTPS to facilitate coal conveyor alignment of proposed 2x660MW SCTPP, CSPGCL Korba West. | 1325018 | 13250 | 19/03/2025 04:00PM | 21/03/2025 04:30PM | 26275 |
| 04:30PM | 04:00PM |
| 8100041200 |
105
| E.D.(Civil-Project-I) Raipur | ED(CP-I)/2x660MW/W/2024-25/T-98 | Dismantling of CC road and side drain from railway gate to store-1 (400M) of 1x500MW Extn. HTPS, to facilitate coal conveyor alignment of proposed 2x660MW SCTPP, CSPGCL Korba West. | 2778393 | 28000 | 19/03/2025 04:00PM | 21/03/2025 04:30PM | 26273 |
| 04:30PM | 04:00PM |
| 8100041198 |
106
| C.E.(Civil: AU&PC) | EDC/AU&PC/DSPM-KE/W/2024/86 | Collection of Cenosphere from Ash Dyke Gorhi/Pandripani at DSPM-TPS, CSPGCL, Korba East. | 2644000 | 106000 | 17/03/2025 03:00PM | 27/03/2025 04:00PM | 26250 |
| 04:00PM | 03:00PM |
| MSTC/RPR/CHHATTISGARH STATE POWER GENERATION COMPANY-CIVIL-GEN/01/RAIPUR/25-26/11 |
107
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/85 | Collection of Cenosphere from ash dyke Dindolbhata of 1x500 MW Extn. HTPS, CSPGCL, Korba West. | 4125000 | 165000 | 17/03/2025 03:00PM | 27/03/2025 04:00PM | 26249 |
| 04:00PM | 03:00PM |
| MSTC/RPR/CHHATTISGARH STATE POWER GENERATION COMPANY-CIVIL-GEN/2/RAIPUR/25-26/12 |
108
| C.E.(Civil: AU&PC) | EDC/AU&PC/DSPM-KE/W/2024/75 | Transportation of pond ash for construction of 4 lanning of NH-130A (Urga-Pathalgoan), CH 121+00 to CH 131+00 from Gorhi-Pandripani ash dyke of DSPM-TPS, CSPGCL, Korba East (Phase-II). | 25969000 | 259700 | 17/03/2025 03:00PM | 19/03/2025 04:00PM | 26248 |
| 04:00PM | 03:00PM |
| 8100041559 |
109
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/78 | Utilization of ash in eco-friendly manner by filling in various low laying area within a distance of 50 Km from ash dyke Dindolbhata 1x500 MW Extn. HTPS, CSGPCL, Korba West. | 42513000 | 425200 | 17/03/2025 03:00PM | 19/03/2025 04:00PM | 26245 |
| 04:00PM | 03:00PM |
| 8100041611 |
110
| C.E.(Civil: AU&PC) | EDC/AU&PC/HTPS-KW/W/2024/77 | Utilization of ash in eco-friendly manner by filling in various low laying area within a distance of 50 Km from ash dyke Jhabu 4x210 MW HTPS, CSPGCL, Korba West. | 44727000 | 447300 | 17/03/2025 03:00PM | 19/03/2025 04:00PM | 26244 |
| 04:00PM | 03:00PM |
| 8100041610 |